Client Challenge
Denso, an existing customer of Besco’s, needed a replacement water softener for their facility. The systems that were in place were 30 years old and had completed their life cycle. Since many operational transitions had occurred over the last 30 years, Besco’s design team assisted the customer in determining what they wanted to see within a new system, as well as flow rates and probable daily usage.
Besco Solution
After working with the customer we determined that we could utilize a single system as opposed to the two systems that were currently in place while still keeping redundancy. We designed a system to fit their needs. As with any CapEx, there would need to be multiple bids. After reviewing all of the bids, the customer chose Besco as their preferred supplier for this project. The other bids did not meet the specifications that they required. Besco worked with the customer and mechanical contractor to lay out the design and parameters for the placement of the system and subsequently performed the start-up and commissioning of the system. Besco worked with the customer and mechanical contractor to lay out the design and parameters for the placement of the system and subsequently performed the start-up and commissioning of the system.
Client Challenge
Amway, a global leader in health and beauty products, required an upgrade to their main water softening system at their XS liquids building. The existing system was a critical component in their production line, serving as a pre-treatment stage for the reverse osmosis system that is integral to the production of their popular energy drinks. Amway needed a solution that would allow them to replace the system without disrupting their tight production schedules.
Besco Solution
Besco Water Treatment was tasked with the challenge of replacing Amway’s water softening system with minimal impact on production. We designed a 1.2M grain twin alternating system that would provide the necessary capacity and reliability for Amway’s operations. To ensure a seamless transition and continuous production, we collaborated with Hunter Prell, our trusted contractor, to implement a strategic installation plan. The plan involved setting up one tank to be operational while the second tank was being installed, thus eliminating any downtime for Amway’s production line.
The result was a flawless installation that did not interfere with Amway’s energy drink production. Besco Water Treatment’s commitment to listening and responding to our customer’s needs was evident in the successful execution of this project. Amway was able to continue their operations uninterrupted, thanks to the new water softening system that now reliably serves as a pre-treatment for their critical reverse osmosis system.
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Client Challenge
Google is a multinational technology company with 78 offices in more than 50 countries. Google.com is the most visited website in the world. But Google is more than a search engine, it is also a software developer, advertising platform and cloud computing platform.
Google’s $1.2 billion data center complex in Lenoir, North Carolina, and a $2.4 billion center in Berkley County, South Carolina, are two branches of a large network of data centers all over the world. They are full of row after row of machines, all working together to make Google function — and giving off massive amounts of heat.
Google’s server rooms must be kept at exacting humidity levels. Too much moisture in the air can damage computer equipment, but a lack of humidity can also cause problems, such as static electricity buildup and electrostatic damage. Data centers typically run constant water misters to keep the humidity level at just the right amount.
Google uses more than 4 billion gallons of water per year. Some of it is used in offices, but most is consumed by its data centers, where Besco Commercial’s high-purity water is sprayed into the air through ultrasonic humidifiers.
Besco Solution
To protect the information on the internet, Google turned to Besco Commercial to supply these ultrasonic misters with high-purity water. Besco’s water treatment experts designed a reverse-osmosis system.
In data centers, water must be purified before it is misted into the air. Any mineral buildup in the humidifier would affect the desired application of fine-mist fog, and could create maintenance issues. Any impurities in the misted water could lead to buildup or deposits on the computer equipment, potentially causing corrosion or damage.
When ultrapure water is necessary for effective humidity control in an IT environment, Besco can custom tailor a solution. Besco Commercial is proud to play a part in protecting Google’s high-performance computers.
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Besco has experience with this type of installation so the added security and assembly requirements could be met while ensuring that the United States would be pleased with the system. Besco won the bid on this project based on cost, reputation and the ability to do this type of “remote installation”. So Besco engineered and assembled the system with the manufacturer at their facility in Doral, Florida. After assembly, it was shipped to the jobsite at the Embassy in Lima, Peru. It was then installed by Peruvian contractors cleared for high security. Once installed, a Besco qualified service technician flew to Peru to perform the programming, start-up and training of the Embassy workers on how to operate the system.
The U.S. Government officials at the Embassy were ecstatic at the level of communication and the smooth and efficient operation of the new filtration and water softener system. They were totally satisfied with the completed project.
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Besco has deep experience with this type of installation so the added security and time requirements could be met while ensuring that the State would be pleased with the installation. So Besco engineered, sold and removed the existing equipment, and then installed the replacement equipment. This new water softener system was completely installed, and was up and running all in one day, due to the meticulous coordination efforts of the Besco Team. Photos were taken prior to the installation so that all materials were present at the time of installation.
An environmental extraction company was scheduled to have the old materials removed and taken away enabling Besco’s team to have the existing system removed and off-site within two hours. The technicians then went to work installing the new system. It was all accomplished by 3:30PM…fully functioning and operational. The coordination and installation of a system this size typically requires a minimum of two days to complete, we did it in one. Besco Commercial Water Treatment can keep a timeline and, because of the volume of systems that we’ve engineered, we know how to do it efficiently and with limited downtime for our customers.
Client Challenge
Besco Solution
Besco Commercial Water Treatment is very familiar with unusual installations for its big commercial customers and is happy to work under all circumstances to satisfy customer requirements regardless of complexity. So, Chase Bank needed a pre-designed system that could be delivered on skids and installed quickly and easily. Secondly, it could only occupy a certain footprint in their data center. Thirdly, it needed full redundancy in the event of failure. Besco Commercial was able to meet all of these requirements and engineered a stainless steel skid that fit Chase’s design and provided redundancy. All the system needed once delivered to the Chase facility was power, a feed line, a process line and a drain…then it was ready to run and produce high quality water for the Chase data facility. Besco kept the installation phase to a bare minimum in keeping with Chase Bank’s requirements, so all face-piping and operational components were pre-wired and plumbed at Besco Commercial’s plant.Please note the picture below of the installation is on a skid at the Besco plant as no photos are permitted in the Chase Bank data center.
Client Challenge
Besco Solution
Client Challenge
Besco Solution
We went in to assess the feasibility of rebuilding their current water treatment system versus replacing it with new equipment. We completed a cost analysis and presented the advantages of upgrading their system with the goals of maintaining consistent water quality, improving efficiency, and creating versatility for potential future growth. Our engineers designed a water treatment system with a computerized control system to monitor flow rates and activate tanks based on water flow to keep up with their varying daily usage pattern.
So, during the slower times when the demand for water is low, only one softening unit is online. As business escalates and the demand for water increases, the Besco-designed control system activates additional softening tanks to satisfy the current demand for water. This ensures that Soapy Joe’s maintains consistent water quality throughout the day and maximizes the efficiency of the system, saving salt and water, by eliminating unnecessary regenerations.
In addition, the design of the system provides for future growth which is very important to this client. The system can be customized to meet increasing water demands. Please view our photos of the installation below.
Client Challenge
Besco Solution
Gratiot Finishing
Detroit, MI
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Besco engineered a “tri-plex demand recall system” that will automatically adjust with the fluctuations of flow rate demand that the senior housing complex has. As the flow rate demand for softened water increases to the peak level of one tank, the system will bring on another tank… up to three… to meet the flow rate demands that are called for.Besco Commercial Water Treatment demolished the existing system and installed the new system closer to the wall to improve space requirements for the facility. Besco then moved the salt storage tanks into an adjacent room and hard-plumbed the brine line to the water system. This move saved Northpointe Woods enough space that they were able to easily access the gated area without any obstructions.
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Leveraging our longstanding relationship with Korex, which includes providing solutions for their plants in Wixom, MI, and Ontario, CAN, Besco Water Treatment was once again entrusted with delivering a state-of-the-art water treatment solution for the Chicago plant. Our team designed and implemented a sophisticated high-purity water system uniquely tailored to meet the demanding requirements of Korex’s production line. The system was engineered to ensure it adheres to the highest standards of cleanliness and efficiency crucial for the production of facial lotions and detergents.To minimize disruption to Korex’s operations, we coordinated a meticulous installation schedule aligned with their production timelines. Our strategic approach allowed for the installation and integration of the new water purification system without any downtime, ensuring continuous production. The installation of the high-purity water system at Korex’s Chicago plant was a resounding success. Korex can now ensure the consistent quality of its products, backed by the reliability and efficiency of Besco’s water treatment solutions. We are proud to be a part of Korex’s commitment to quality and excellence, and we remain steadfast in our dedication to ensuring they remain at the forefront of their industry.
Arcadia Brewing
Kalamazoo, MI
Client Challenge
Besco Solution
Besco designed and installed a chlorination and organic removal system for the new Arcadia Brewing Company located in Kalamazoo, MI.Besco Commercial Water Treatment installed a 42” diameter carbon backwash system with a 2” control valve. The valve will capture pertinent information such as average gpm, total water usage, average flow rate, and the number of backwashes since start up. All of this information is instrumental in the diagnostic process of Arcadia Brewing Company.
Two weeks after the install Besco followed up on the new system to be certain that it was producing as promised. It was. The system is working as specified and Arcadia has brewed many batches utilizing Besco Commercial Water Treatment’s designed system.
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Client Challenge
Besco Solution
Client Challenge
Besco Solution
When working with its international customers Besco realizes that not only do the application specifications need to be met, but the installation must seamlessly interface with other internal systems and be designed for the utmost safety of the customer’s work force. This system was designed with special safeguards to do just that.
To solve Gerber Baby Products needs, Besco designed and built a stainless steel system with high temperature solenoid values, face-piping and a PLC controller that can be monitored and controlled from the customer’s BMS system. Since this system required extensive programming, Besco outsourced a programmer from Texas to write custom code for this application to ensure that all functions interface with the current operating system at Gerber.
In addition, when dealing with high temperatures such as were required here, many safeguards were built into the system to prevent injury in case of a failure. These safeguards were designed and customized by Besco Commercial in a redundant fashion so that in the event of a steam leak, the system would automatically shut itself down.