Client Challenge
Both Korex facilities required 20 gpm high purity systems for their batching process. The quality requirement was 1 megohm resistivity continuous flow.
Besco Solution
Besco engineered a system consisting of reverse osmosis technology, pre-treatment, deionization, ultraviolet and sub-micron filtration. In the interim, while the system was being installed, Besco provided high flow jumbo deionization tanks for the temporary plant so that production could begin immediately.